Small prototype testing was performed in Trondheimsfjord in August 2003. Two anchors of approximately 1/3 the expected average full size anchor i.e. 4.4m long and approximately 2.8 tons, were machined and fabricated at REINERTSEN Orkanger for testing and verification of the procedures involving prototype installation and anchor behavior during deployment and service. The test was carried out on borehole G08 in a proposed gas pipeline route through Trondheimsfjord to Skogn, about 5,5 nautical miles from Port of Trondheim.
The test program is divided into to parts i.e.
The anchor was instrumented with:
The tests were well carried out and satisfied its goals which are to implement and execute the proposed procedures and associated equipment for fabrication, transportation and installation of the anchor. Furthermore, the geotechnical assessment to verify the anchor penetration depth and holding capacities was conducted. The pull-out-tests were carried at time 0 (right after drop), 1 week after drop, and 2 weeks after drop, both laterally and vertically. In general, the results from the test conformed the expected capacity of such DPA.